Capital budgeting: the process a business uses to decide which long-term projects or investments (machines, factories, software) are worth their cost.

The NPV Formula, Symbol by Symbol

NPV = Σ CFt ÷ (1 + r)t − Initial investment
NPVNet Present Value — value created by the project in today’s money.
CFtCash flow expected in year t.
rDiscount rate — the required return or cost of capital (Lesson 10).
tYear number: 1, 2, 3…
Initial investmentCash spent today (year 0).
RuleNPV > 0 → accept; NPV < 0 → reject.

Worked Example: A $10,000 Machine

The machine costs $10,000 and adds $4,500 cash per year for 3 years. Required return 10%.

YearCash flow÷ (1.1)tPresent value
14,5001.1004,090.91
24,5001.2103,719.01
34,5001.3313,380.92
Total PV11,190.83

NPV = 11,190.83 − 10,000 = +$1,190.83 → accept. The project creates about $1,191 of value in today’s money.

IRR: Internal Rate of Return

IRR = the rate r where NPV = 0
RuleIRR > required return → accept.
HowTrial and error, or Excel =IRR().

For our machine: at 16% NPV is slightly positive, at 17% slightly negative → IRR ≈ 16.65%. Since 16.65% > 10%, accept.

Payback Period and Profitability Index

Payback period

Initial investment ÷ annual cash flow = 10,000 ÷ 4,500 = 2.22 years. Simple, but ignores time value and cash after payback.

Profitability index

PV of inflows ÷ Investment = 11,190.83 ÷ 10,000 = 1.12. Above 1 → accept. Useful when capital is limited.

Which Method Should You Trust?

MethodUses TVM?StrengthWeakness
NPVYesMeasures value in $ — the best ruleNeeds a discount rate
IRRYesEasy % to explainCan mislead with unusual cash flows or when ranking projects
PaybackNoSimple, shows liquidity riskIgnores later cash and TVM
PIYesRanks projects under a budget limitIgnores project size

When NPV and IRR disagree, follow NPV.

Interview Questions

What does a positive NPV mean?

The project’s discounted cash inflows exceed its cost, so it is expected to create value above the required return.

What is IRR?

The discount rate that makes a project’s NPV exactly zero — its expected annual rate of return.

Why is NPV preferred over IRR?

NPV measures value in currency and handles different project sizes and unusual cash flows correctly; IRR can give multiple answers or rank mutually exclusive projects wrongly.

What is the main weakness of the payback period?

It ignores the time value of money and any cash flows after the payback point.

What discount rate should you use for NPV?

The project’s required return, usually the company’s cost of capital (WACC) adjusted for the project’s risk.

Exam Quick Revision

  • NPV = Σ CF/(1+r)^t − Investment; accept if > 0.
  • Example: PV 11,190.83 − 10,000 = NPV 1,190.83.
  • IRR = rate where NPV = 0 (≈ 16.65%).
  • Payback = Investment ÷ annual CF (2.22 yrs).
  • PI = PV inflows ÷ Investment (1.12).
  • If NPV and IRR conflict, use NPV.